EPS@ISEP | The European Project Semester (EPS) at ISEP


Table of Contents

Work plan

Deadlines

  • 2015-03-02 Choose a project proposal and send the result via email to epsatisep@gmail.com
  • 2015-03-11 Define the Tasks (what must be done), Task allocation (who does what) and Gantt chart (when) of the project and insert them on the wiki (planning)
  • 2015-03-27 Specify the list of material (what, quantity, where to buy - local companies are mandatory) on the wiki
  • 2015-04-05 Upload the Interim Report and Presentation to the wiki; the report should contain the Introduction, including the tasks, team members allocation and Gantt chart, State of the Art, Marketing Plan, Project Management, Eco-eficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography chapters
  • 2015-04-09 Interim Presentation, Discussion and Assessment
  • 2015-06-12 Upload the Final Report, Presentation, Video, Paper, Poster and Manual
  • 2015-06-18 Final Presentation, Individual Discussion and Assessment
  • 2015-06-25:
    1. Update the wiki with all correction suggestions
    2. Hand in a CD with the corrected deliverables (source + PDF) together with all code produced to the EPS coordinator
    3. Hand in one printed exemplar of the corrected report to the EPS coordinator
  • 2015-06-26:
    1. Hand in the prototype and user manual to the client
    2. Receive the EPS@ISEP certificate

Tasks

Task Responsible
meetingsall
planningsall
research
materialPaloma
technologiesBartek, Eughan
identityAnthony
life-cycleall
requirementsall
targetall
brief
identityAnthony
objectivesall
implementation
marketingCarina
materialsPaloma, Eughan, Bartek
programmingEughan, Bartek
constructionPaloma, Carina
safetyall
testing/controlling
distribution
internetAnthony, Carina, Kristjan
marketingCarina

Gantt Chart

WEEK 22/06/2015 - 26/06/2015 GANTT CHART

QR Code
QR Code plan (generated for current page)